Reading a Tender Pack Before You Price: A Subcontractor's Guide
A practical guide for subcontractors with a tender enquiry in hand: what is usually in the pack, what to look for in each document, and how to turn what you find into queries, assumptions and a decision on whether to price.
What should a subcontractor read in a tender pack before pricing?
Start with the tender instructions: the submission date and time, the pricing format, the query deadline and how long the price must stay open. Then check you have every drawing on the register and note each revision and status, read the specification for any design or performance requirements, read the bill preambles and check your trade's quantities where you can, list what the preliminaries say the main contractor provides, and read the subcontract terms and amendments for payment, retention, delay damages, insurances and bonds. Check the programme and site information. Send gaps and conflicts as written queries before the query deadline, state the assumptions your price depends on, and decide whether to price, price with qualifications or decline. Whether quantity errors are your risk, and which document wins where they disagree, depends on the subcontract. General information, not legal advice; the law in Scotland differs in places. Take advice if the terms are unclear or the job is large.
How we handle this: Estimating and tender pricing
Read on from this guide
- The Pack Is What You Are Pricing: What to list with your tender price
- Bill of Quantities or Pricing Schedule: Building up a rate for each item
- Subcontract Terms and Amendments: How delay damages work for subcontractors
- Where the Documents Disagree: Writing assumptions and qualifications
Related guides
- Building Up a Rate for a Subcontract Tender: The five parts of a unit rate, where overheads and margin go, and one rate built up line by line.
- Tender Qualifications and Exclusions: What to state with your price, and how to make sure your qualifications end up in the contract you sign.
- Liquidated Damages: Challenging a Delay Deduction: How delay damages work in a subcontract, and when a deduction from your payment can be challenged.
- Retention: When retention falls due, how to chase it and what to do when it is withheld.
- Valuing Variations Without Losing Margin: How to record change properly, price it on a defensible basis, and stop extras leaking into dispute.
Questions we hear all the time
- What is a tender pack?
- The documents a main contractor sends with a tender enquiry so you can price a package: usually the tender instructions, drawings, a specification, a bill of quantities or pricing schedule, the preliminaries, the proposed subcontract terms and a programme, with any site information. What is included varies from job to job, so check what you have against what you need before you start.
- The drawings are marked preliminary or for information. Can I price from them?
- You can, but they may still change. Say in your tender which drawings and revisions you priced and that they were not issued for construction, so that, if your tender list forms part of the subcontract, a later revision can be shown and valued as a change.
- Do I carry the risk if the quantities in the bill are wrong?
- It depends on the subcontract. Some say the work will be remeasured, so the quantities are adjusted to what is actually done. Others treat your price as a lump sum for the work shown. If the bill is for information only, or the contract does not say how errors in it are corrected, a quantity you did not check may be your risk. Read the bill preambles and the subcontract, and take advice if the terms are unclear.
- The pack does not include the subcontract terms. Can I still price?
- Yes, but ask for them, because payment terms, retention, delay damages and insurance requirements all affect your price. If they do not arrive before you submit, say in your tender that your price has not allowed for terms you have not seen and is subject to agreeing them.
- The specification asks me to design part of the work. What should I check?
- Check exactly which part is your design, the standard it must meet, who checks or approves it, whether the standard is reasonable skill and care or fitness for purpose, and whether your professional indemnity insurance covers it. Price the design time and any specialist input. Design responsibility in a subcontract is worth taking advice on before you sign. Subcontract review before you sign
- Can you read the tender pack for us?
- Yes, as part of a paid estimating instruction. We start by reviewing the tender: we confirm the documents, the trade scope and the submission deadline, measure the work and build the rates, and flag gaps or conflicting information in the tender documents so you can raise them before you submit. Send what you have and we tell you if anything is missing. Reviewing the subcontract terms themselves is a separate service. Our estimating service
- Is this guide legal advice?
- No. It is practical guidance on reading tender documents before you price. Which documents bind you, and what they mean, depends on the contract you finally agree, so take advice if the terms are unclear or the job is large. The points here are general, and the law in Scotland differs in places.