Building Up a Rate for a Subcontract Tender
A practical guide for subcontractors pricing a package: the five parts of a unit rate, how to work out labour, materials and plant from your own figures, where overheads and margin go, and one rate built up line by line.
How does a subcontractor build up a rate for a tender?
Build each rate for the bill's unit, from direct cost up. Labour is the output per unit times your all-in hourly cost (pay plus employer's National Insurance, pension, holiday pay and other employment costs, spread over hours worked on site), adjusted for height, access and repetition. Materials are the quantity per unit plus waste, delivery and fixings, priced from quotes checked against how long your price must stay open. Small tools can go in the rate; plant hired for the length of the job and time-related costs usually go in the preliminaries. Add overheads on one consistent basis, so nothing is counted twice, and margin once, on purpose. Price or qualify risks separately, and keep the build-up: where the subcontract values changes from your rates, it is where a fair rate starts. General information, not legal advice; the law in Scotland differs in places. Take advice if the terms are unclear or the job is large.
How we handle this: Estimating and tender pricing
Read on from this guide
- Start From the Measured Unit: What to read in the tender pack first
- Margin: Added Once, and Decided on Purpose: Qualifying a risk with your price
- Keep the Build-Up When You Submit: Valuing variations from your rates
Related guides
- Reading a Tender Pack Before You Price: What is usually in the pack, what to look for in each document, and how to turn it into queries and assumptions.
- Tender Qualifications and Exclusions: What to state with your price, and how to make sure your qualifications end up in the contract you sign.
- Valuing Variations Without Losing Margin: How to record change properly, price it on a defensible basis, and stop extras leaking into dispute.
- Dayworks: Getting daywork sheets instructed, signed and into an application.
Questions we hear all the time
- What is an all-in labour rate?
- The full hourly cost of an operative to your business, not just their pay. For employed staff it adds the costs that come with employing them, such as employer's National Insurance, pension contributions, holiday pay, sick pay, the CITB levy if you pay it, PPE and training, and any travel or allowances you pay, spread over the hours they actually work on site. It is the figure to multiply by the output when you build a rate.
- Should overheads and margin go into every rate or at the end?
- Either can work, as long as you are consistent and nothing is counted twice. Many estimators put overheads into the rates and add margin once on the total, as our sample estimate does, so the margin can be reviewed before submission. Check the tender instructions first: some say how the price must be set out.
- How much waste should I allow?
- It depends on the material, the layout and how the work is measured. Small rooms, lots of cutting and materials sold in fixed lengths or sheets usually waste more. Your own records of what was ordered against what was measured on past jobs tell you most.
- Is my price fixed if material prices go up before I start?
- Often, yes. Unless the subcontract allows for price changes (some standard forms let the parties choose fluctuation provisions that adjust for rises in labour or material costs, and those only apply if chosen in the contract details), your price is likely to be fixed. If the start date is a long way off or a material is volatile, say in your tender how long your price holds and what it assumes, and take advice if the terms are unclear. What to state with your price
- Will my rates be used to value changes later?
- It depends on the subcontract. Under many subcontracts, including the standard JCT subcontracts, if no price is agreed first, changes are valued using the rates in your priced document where the changed work is of a similar character, done under similar conditions and does not significantly change the quantity. Where conditions or quantities differ, your rates are still the starting point, with a fair allowance for the difference, and work of a different character is valued at fair rates and prices. So a rate cut to win the job can follow you into the valuation of changes. NEC subcontracts assess most changes differently, mainly on the actual and forecast cost of the change plus your fee, and your rates are used instead only if you and the contractor agree. On an NEC subcontract priced with a bill of quantities, though, the work is remeasured, so where a bill quantity simply turns out to be wrong, rather than the work being changed, the actual quantity is paid at your bill rates, unless the difference is large enough to change your cost per unit, when the rate itself can be reassessed. Read the valuation terms before you price. Valuing variations
- Can you build the rates for us?
- Yes, as part of a paid estimating instruction. We measure the work and build the rates, and the estimate we send back shows the materials, labour, plant and overhead allowances behind each rate, with clear qualifications and exclusions. We can also review a price you have already put together and check your allowances and margin before the tender goes in. Our estimating service
- Is this guide legal or financial advice?
- No. It is practical guidance on building up rates for a tender. The figures in the worked example are made up to show the method. What your price covers, and how changes are valued, depends on the contract you finally agree, so take advice if the terms are unclear or the job is large. The points here are general, and the law in Scotland differs in places.