Variations on Construction Contracts
How to identify, value and claim for variations as a subcontractor, including instructions, change control, fair valuation and dealing with unagreed work.
How are variations valued and paid on a construction subcontract?
By the valuation rules in your subcontract. Under the JCT Standard Building Sub-Contract (SBCSub/C), work of a similar character, under similar conditions and without a significant change in quantity, is valued at subcontract rates; otherwise at those rates with a fair allowance or at fair rates; as daywork where it cannot properly be valued by measurement. NEC4 subcontracts treat most changes as compensation events, valued on their effect on Defined Cost plus the fee; a late notice can bar some events. If nothing prices it, a reasonable sum is usually implied. Confirm instructions in writing as your subcontract requires, then put the variation in your next application. For contracts entered into on or after 1 October 2011 in England and Wales (1 November 2011 in Scotland), without a payment notice, your application or a default notice can become the notified sum, and paying less needs a pay less notice in time. A homeowner's own contract is excluded, not your subcontract.
How we handle this: Variation claims for subcontractors
Loading the full Contract Group experience…