Tracking Payment Applications and Notices
A practical guide for subcontractors in England and Wales: what to record for every payment application, where the due date, notice deadlines and final date come from, and what to check when a date passes. With a free tracker spreadsheet.
How should a subcontractor keep track of payment applications and notices?
Add one row per application the day you send it: what you applied for and when, the due date, each notice's deadline, arrival and amount, the final date, what was paid and when, and notes. Take the periods from your contract. Where it leaves a payment term out, or one does not comply with the Construction Act, the Scheme for Construction Contracts supplies it: in England and Wales, a payment notice no later than 5 days after the due date, a final date 17 days after the due date and a pay less notice no later than 7 days before the final date. If you have to give your own payment notice, the final date moves later. A tracker shows where to look, not whether a notice is valid. Not legal advice; some contracts are outside the Act, and Scotland and Northern Ireland have their own Schemes. Take advice if the terms are unclear or the sum matters.
How we handle this: Quantity surveying for subcontractors
Read on from this guide
- The Dates Decide What Is Owed: How payment and pay less notices work
- Read the Payment Clause: Where the dates are in a JCT subcontract
- Where the Contract Says Nothing: Check the dates with the free payment deadline calculator
Related guides
- How to Write a Payment Application That Stands Up: What a strong application includes, and how to send it so it counts.
- Payment Notices and Pay Less Notices: Who gives which notice, when, and what happens if one is missed.
- Disputing a Pay Less Notice: How to check a pay less notice and challenge one that is late or invalid.
- Interest on Late Payment: What you can claim when you are paid after the final date.
Questions we hear all the time
- What should a payment application register include?
- One row per application, with the application number, valuation date, date sent, the due date your contract gives, when the payment notice was due and received and its amount, the final date for payment, when any pay less notice was due and received and its amount, the amount applied, the amount paid and the date paid, and notes. Our free tracker has these columns ready, with the deadlines worked out from the periods you type in.
- What if no payment notice arrives?
- Where your contract requires the paying party to give the payment notice: if your contract let you send your application before the payment notice was due and you sent it as your contract requires, stating the sum and how it was worked out, your application usually becomes the notified sum: what you must be paid by the final date unless a valid pay less notice is given in time (sections 110B and 111 of the Construction Act). If not, you can give your own notice stating the sum you consider due and the basis on which it is calculated, but the final date for payment then moves later by the number of days after the payment notice deadline that you gave it. Check your contract, and take advice if the sum matters. Payment and pay less notices
- What if a pay less notice arrives late?
- A pay less notice given after the deadline the contract sets, or the Scheme's deadline where the contract sets none, does not let the paying party pay less than the notified sum for that payment. It is still worth recording, and reading, because what it says may come up again in a later payment or the final account. Whether a notice was valid can turn on its wording and how it was given, so take advice before you rely on it. Challenging a pay less notice
- What if I am paid after the final date?
- Record the date the money reached you. If the notified sum, or the sum stated in a valid pay less notice, is not paid in full by the final date, you may be able to claim interest, either under your contract or under the late payment legislation where the contract has no substantial remedy, and section 112 gives a right to suspend some or all of your work after giving at least 7 days' notice of your intention to suspend, stating the grounds. Suspending without a valid right can put you in breach, so take advice before you serve a notice. Interest on late payment
- Does the tracker tell me whether a notice is valid?
- No. It works out dates from the periods you type and compares amounts and dates. Whether a notice was given in time, contains what it must and was given in the way the contract requires depends on the contract and the notice itself. The tracker shows you where to look.
- Can you keep on top of this for us?
- Yes. Preparing each application from your records, organising the notices and records your contract requires, and reviewing the responses that come back each period is quantity surveying work we do for subcontractors. That work is paid, booked by the hour or day, or under a plan. Quantity surveying for subcontractors
- Is this guide legal advice?
- No. It is practical guidance on keeping a record of applications, notices and payments. The dates that apply depend on the contract you signed, and the rules described here are those for England and Wales; the law in Scotland and Northern Ireland differs in places. Take advice if the terms are unclear or the sum matters.