What should I do when I receive a notice of adjudication?

Take advice at once and read your contract's adjudication clause and any rules it adopts: they may set their own dates, including for your response. Where the clause falls short of the Construction Act, the Scheme for Construction Contracts applies: the referral notice must be sent to the adjudicator no later than 7 days from the date of the notice, and the adjudicator must decide within 28 days of receiving it unless that time is extended. The Scheme sets no deadline for your response: the adjudicator sets the timetable and can carry on without you if you miss it, so ask early for more time. Object to the adjudicator's jurisdiction in writing at the start, listing each objection, and say that you take part without accepting it. Comply with the decision when it arrives: it binds you until the dispute is finally decided by a court, arbitration or agreement. General information for England and Wales, not legal advice.

How we handle this: Adjudication and arbitration

Read on from this guide

Related guides

Questions we hear all the time

How long do I have to respond to a notice of adjudication?
Neither the Construction Act nor the Scheme for Construction Contracts sets a fixed period. The adjudicator sets the timetable once the dispute is referred. Under the Scheme the referral must follow within 7 days of the notice and the decision is due 28 days after the adjudicator receives the referral, unless that is extended, so start preparing the day the notice arrives.
Can I refuse to take part?
You can, but the adjudication carries on without you. Under the Scheme the adjudicator can continue, draw inferences from your silence and decide on the information supplied, and the decision binds you in the same way. If you think the adjudicator has no power to decide the dispute, it is usually safer to say so in writing and take part without accepting jurisdiction. Take advice before deciding.
Can the deadline for the decision be extended?
Under the Scheme the 28 days can become 42 days only if the referring party consents, or a longer period if both parties agree after the referral. You can ask the adjudicator for more time for your own response, but the decision date does not move unless that consent or agreement is given.
Who pays the adjudicator's fees?
Under the Scheme the adjudicator decides a reasonable amount for their fees and expenses and, unless a valid contract term says otherwise, how it is split between the parties. Whatever the contract says, both parties remain liable to the adjudicator for any part left unpaid. Each party normally pays its own costs. For contracts made on or after 1 October 2011, a term making one party pay the other's costs only counts if it is in writing and was agreed after the notice of adjudication was given (section 108A of the Construction Act). If both sides ask the adjudicator for their costs in writing, that may count as such an agreement, so take advice before claiming them.
What if I think the adjudicator has no jurisdiction?
Say so in writing as soon as you can, give your reasons, and say that you take part without accepting jurisdiction. The adjudicator can consider the point, but if the other side later asks a court to enforce the decision, the court decides whether the adjudicator had the power to make it. Do not agree to the adjudicator deciding the jurisdiction point bindingly; ask only for a non-binding view. Taking part without objecting can lose you the argument.
Does this guide apply in Scotland or Northern Ireland?
It is written for England and Wales. The Construction Act also applies to construction contracts for work in Scotland, where the Scheme for Construction Contracts (Scotland) Regulations 1998 fill any gap in the contract, so the same statutory right to adjudicate applies but the details differ. Northern Ireland has its own legislation, the Construction Contracts (Northern Ireland) Order 1997, with its own Scheme and courts. Take advice specific to where the work is. How a decision is enforced in Scotland
Is this guide legal advice?
No. It is general information about the Construction Act and the Scheme. Your contract may have its own adjudication rules, and some rules described here changed for contracts made on or after 1 October 2011, so if your contract is older, take advice. The time to respond is short, so take advice as soon as the notice arrives.