Getting Paid Under an NEC Subcontract
A plain-English guide for subcontractors in England, Wales and Scotland on an NEC4 subcontract: which form you are on, how assessments and certificates decide what is due, and the notices the Construction Act requires.
How do payment dates and notices work under an NEC subcontract?
NEC4 subcontract payment runs on assessment dates in the Subcontract Data, which Z clauses can amend. Under the full form the main contractor assesses, and NEC's own published guidance says the due date is 14 days after the assessment date. Under the Short Subcontract you assess and, where the Construction Act provisions apply, your application is the payment notice, so sending none can make the notified sum zero. For subcontracts entered into on or after 1 October 2011 in England and Wales (1 November 2011 in Scotland), the Act requires the subcontract to provide for a notice of the sum considered due and its basis no later than 5 days after each due date (section 110A). To pay less, the payer must give a pay less notice stating the sum and its basis by the subcontract's deadline before the final date (section 111). If the subcontract sets no final date, the Scheme makes it 17 days after the due date.
How we handle this: Payment applications and final accounts
Related guides
- Getting Paid Under a JCT Subcontract: Where a JCT subcontract sets your payment dates, and what applies when an amended subcontract leaves a gap.
- Payment and Pay Less Notices: The notice deadlines that decide whether a sum is due, and what happens when a notice is late or missing.
- Writing a Payment Application: What to include in each application so the sum and its basis are clear.
- Extension of Time Notices: How to claim more time, and why under NEC time and money are assessed together.
- How Adjudication Works: From notice of adjudication to a decision, normally due 28 days after the dispute is referred, and how a decision is enforced.
Questions we hear all the time
- How does payment work under an NEC subcontract?
- Payment runs on assessment dates set through the Subcontract Data. You apply before each assessment date, the amount due is assessed (by the main contractor under the full Engineering and Construction Subcontract, and by you under the Short Subcontract), and a payment then falls due and must be paid by the final date. Where the Construction Act applies, the subcontract must also provide for a payment notice, and the main contractor must give a pay less notice to pay less than the notified sum, and amendments often change the periods, so read the version you signed.
- What is Option Y(UK)2?
- It is the NEC secondary option written for contracts that must follow the payment provisions of the Construction Act. In the full NEC forms it usually sets the due date and the final date, makes the certificate the payment notice and provides for a pay less notice; check the version in your subcontract. If your subcontract is for construction operations in England, Wales or Scotland (and no exclusion in the Act applies) and leaves it out, the Act still applies and the relevant Scheme fills any gap. Northern Ireland has its own legislation (the Construction Contracts (Northern Ireland) Order 1997), so this guide does not cover it.
- What if no certificate or payment notice arrives?
- If you applied under the subcontract before the main contractor's notice was due, stating the sum and how you worked it out, section 110B(4) treats your application as the notice and the sum in it becomes the notified sum. If not, section 110B lets you give a default notice stating the sum you consider due and how you worked it out, and the final date is postponed (moves later) by the number of days between the deadline for the main contractor's notice and the day you give yours. Either way, the main contractor must then pay that sum by the final date (postponed, if you gave a default notice) unless it gives a valid pay less notice in time. If it is not paid, you can refer the dispute to adjudication at any time (section 108). Under the Short Subcontract your own application is the payment notice, so there is no default notice to give: make sure each application goes in on time.
- My application went in after the assessment date. What happens?
- It depends on the wording you signed. Under NEC4 a late or missing application can limit what is due at that assessment date, in some forms to the lower of the amount due at the previous assessment and the main contractor's own assessment, so the payment for that period can be nil, and under the Short Subcontract, where you make the assessment, a missing application may leave nothing new to pay. On cumulative assessments the work can usually be included at the next date, but you lose that period's cash flow. Read the application rule and any Z clause before the next assessment date and diarise it.
- Can the main contractor pay me only when the client pays it?
- Generally no. Section 113 of the Construction Act makes pay-when-paid clauses ineffective unless a payer further up the chain is insolvent, and section 110(1A) stops payment being made conditional on whether obligations (other than payment) under another contract have been performed, or on a decision (such as a certificate issued under the main contract) about whether they have. If an NEC subcontract has been amended with a Z clause that says otherwise, take advice on that clause.
- Where can I read the NEC subcontract I signed?
- NEC contracts are paid publications, so the full text is not free to read online. Ask the main contractor in writing for a copy of the subcontract as signed, including the completed Subcontract Data and any Z clauses. You need all of them to work out your dates.
- Is this guide legal advice?
- No. It is general information about the Construction Act and how NEC4 subcontracts usually work. Where the sums are significant, or the subcontract is heavily amended, take advice before relying on a notice, suspending work or starting adjudication.